You are on PERI's international website. Click here to switch to PERI USA. Click here to view all PERI websites.

BBI Airport, Berlin Brandenburg, Germany

Dados de projecto

Localização: Berlin, Alemanha

Terminal for the new Berlin Brandenburg International Airport

Extension area: 970 ha

Requisitos

  • terminal shell with a construction schedule of just 12 months
  • huge volume of formwork and scaffolding material within the shortest period
  • due to static reasons, most of the slab areas had to be concreted in one pour together with the main and secondary beams

Cliente

BAM Deutschland AG, Stuttgart

Benefícios para o cliente

  • at peak times 8,000 m² of slabs were formed, concreted and realised per week
  • reduced on-site material requirements plus cost savings thanks to coordination by PERI Project Manager in close cooperation with the Site Manager
Jürgen Feierle, Project Manager
Jürgen Feierle
Project Manager

With the PERI slab table solution at peak times we are realising 8,000 m² of slab formwork per week – with all beams and with floor heights of up to 7 m. By combining with SKYDECK we are even able to continue working in strong winds without interruption and can also minimise crane dependency. PERI construction site support offers us technical solutions in the shortest time and also supplies large volumes of materials within just 2 days.

Soluções PERI

  • delivery of large quantities of materials optimised to the necessary on-site requirements
  • formwork and scaffolding solution for foundations, columns and slabs incl. beams
  • provision of a total of 2,700 pre-assembled slab tables delivered just-in-time to the construction site
  • appointment of a Project Manager to support the Site Manager in planning material requirements